Building a stable — how to run the project step by step

Building a stable — how to run the project step by step

We guide clients through every decision that has to be made — from the first sketch of the loose box layout to the day the first horse walks in.

Let’s start with what we do not do

We are not a main contractor. We do not erect arenas, we do not pour foundations, and we do not take responsibility for the building site. If you are looking for a company that will take on a turnkey project and hand over a finished yard — that is not us.

We do something different, and in our view more important: we guide you through every decision this project requires. We advise, design, specify solutions and supply the equipment. You run the build. We make sure you do not take a single decision in the dark.

The most expensive mistakes are not made on site — they are made at the desk, before anyone picks up a spade.

The wrong eaves height, an arena entrance that is too narrow, a loose box half a metre too small. The contractor will build exactly what is in the drawings. The question is who made sure the drawings contain what they should.

Seven stages of the project — and what we do at each

STAGE 1

Brief

You: decide how many horses and what for — sport, breeding, livery, leisure.

We: translate that into technical requirements. From one number — how many horses are to be worked each day — follows almost everything else in the design: the size of the arena, the number of wash bays, whether a horse walker makes sense, how many staff will be needed.

Zdjęcie Zdjęcie Equitex 2 — Building a stable — how to run the project step by step

STAGE 2

Ground and conditions

You: commission a geotechnical survey and check the planning conditions.

We: tell you what to look for. The stabilised layer under the arena must carry 40 kN/m² — if the native ground cannot provide that, soil replacement and compaction are added. It is the cheapest survey in the whole project and the only one that protects you from the most expensive surprise.

STAGE 3

Functional layout

You: work with the architect.

We: sit down to it together with you. At this stage three routes are drawn: the route of the horse, the route of people and the route of manure. If the manure route crosses the hay route, the yard will be awkward to run for its entire life — and putting it right means rebuilding.

STAGE 4

Choosing the arena surface — earlier than you think

You: make the decision.

We: show you three surface systems and the running costs of each. The surface determines the sub-base, the drainage and the width of the entrance for machinery. An arena building ordered without this knowledge later has to be bent to fit the surface, instead of the other way round.

Podloze OTTO Kuraszkow — Building a stable — how to run the project step by step

STAGE 5

Arena structure

You: choose and appoint the contractor for the structure.

We: give you a list of things to check in the quotation — column spacing, eaves height, width of the entrance door, the fixing method for the kickboards, and provision for mirrors and lighting. Four sentences in the enquiry that decide whether the interior can be equipped properly. If you are looking for a contractor for the structure, here we describe the solution we work with most often: the Borga indoor arena building.

Mikołó stajnia2 — Building a stable — how to run the project step by step

STAGE 6

Stable fit-out and equipment

You: approve the scope.

We: design, supply and coordinate installation: loose boxes, stable fronts, doors and windows, kickboards, mirrors, horse walkers, treadmills, manure removal, fencing. Here we take full responsibility for the product and the deadline.

STAGE 7

Commissioning

You: bring in the horses.

We: hand over the facility, train your staff on the equipment and stay on for servicing. A horse walker, treadmill or solarium works every day for years — it needs someone who will answer the phone in year three.

Karuzela Konie bez dopłat korzystają codziennie z karuzeli — Building a stable — how to run the project step by step

Five decisions that cannot be undone

Everything in the project can be improved at some point — except these:

1
Loose box size
An arena can be added, a surface replaced. A 3×4 m loose box stays for 20–30 years. For sport horses, and wherever a horse is stabled for long periods, 3.5×4 m is not a luxury — the horse must be able to lie flat and get up without hitting the wall.
2
Ventilation
A stable without controlled natural ventilation cannot be put right without altering the roof structure. The consequence is respiratory problems along an entire row of boxes.
3
Width of the arena entrance
If the arena leveller cannot get in, the surface will be levelled by hand or not at all. All it took was to plan the door one metre wider.
4
The manure route
With 20 horses that is well over ten tonnes a month. A poor layout of internal routes is a daily nuisance for the whole life of the yard.
5
Sub-base under the surface
The load-bearing layer and the drainage are underneath. Replacing the top layer is one day’s work; correcting the sub-base means taking up the whole arena.

What drives the budget

We do not quote a single price for a whole stable — not because we are hiding it, but because two stables for the same number of horses can differ in budget by a factor of two. Giving one figure would mislead you at the stage where a mistake is most expensive. Individual elements — the arena surface, a modular stable, a lunge pen or fencing — you can price straight away in our configurators.

Instead of a single figure — a map of what shapes the budget:

ItemWhat raises it most
Groundpoor bearing capacity, high groundwater, the need to replace the soil
Utilitiesdistance to the connections; a treadmill requires a 5-pin 16 A supply
Structureclear span, eaves height, standard of finish
Stable fit-outspecification of the loose box, powder coating, sliding systems
Arena surfacethe system chosen and whether the sub-base already exists
Equipmenthorse walker, solarium, treadmill, automated manure removal
Ancillary roomstack room, hay store (fire-safety requirements), wash bays, staff rooms

It is worth thinking beyond the purchase price: what counts is the running cost. A surface that needs no watering and no daily levelling, costs more to buy and less over the next ten years. In our quotation we show both sets of figures.

PODLOZE — Building a stable — how to run the project step by step

Cross-section of a typical arena surface. The riding layer is a few centimetres on top — the rest is construction.

How to start

We cannot advise on the basis of “I want a stable for 20 horses”. We can if you tell us:

  • how many horses and in which discipline,
  • whether you are building from scratch or equipping a yard that already stands,
  • what the ground is like and whether utilities are available,
  • what stage you are at today — idea, plot, design, building shell,
  • when the yard is due to open.

The first conversation is free and usually ends with a list of things to check before you spend your first penny.

Frequently asked questions

No. We are not a main contractor — we do not erect the structure or run the building site. We guide the client through the decisions at every stage, design the interior of the facility and supply the equipment: stable fit-out, arena surfaces, training equipment and fencing. Your contractor runs the build — we make sure they know what they are supposed to build.

Ideally before the arena structure is ordered, and better still before the design. Column spacing, eaves height and the width of the entrance determine how the interior can be equipped — and once the structure has been ordered, those parameters cannot be changed. We also work with buildings that are already standing, but then there is less room for manoeuvre.

No. A large part of our work is retrofitting and modernising existing yards: replacing the arena surface, installing kickboards, adding a horse walker, replacing loose box fronts and partitions, automating manure removal.

Typically 8–10 weeks from order. The timing of the other stages depends on your building contractor and on the procedures at your local authority.

Yes, and for most private projects it is a sensible route. One condition: the phasing has to be planned from the start. Utility connections, drainage and the layout of internal roads must be built for the final scale — otherwise phase two means digging up phase one.

Yes. We act as a technical adviser — we raise comments on horse welfare, fire safety, ventilation, daylighting and running costs before the documentation is closed.