About the film
How a surface is built on an outdoor arena: laying perforated mats on the sub-base, drone view. Arena surfaces: Arena surfaces
Sequence of work on an outdoor arena:
- aggregate sub-base with a load-bearing capacity of 40 kN/m², laid to a 1% fall
- ø 10 cm drains every 10–20 m in geotextile and a 7 cm drainage layer of 6–18 mm aggregate
- 4–5 cm perforated mats with a 3 cm expansion gap
- riding layer: quartz sand with geotextile fibre, 8–10 cm
The mat separates the riding layer from the sub-base, so the sand does not migrate downwards, drainage is even and the hoof does not punch through to the sub-base.
In the configurator on the website you can check the indicative cost of material with delivery.